| Date |
Who |
Purpose |
Remarks |
| 18/19th February |
Timbmet |
First visit, test framework |
Formal agreements need to be signed quickly - done 18/2 |
| 24-28th February |
Latham |
First visit |
Done 4/3 - need to send back summary |
| 2nd week of March |
Andy in CameroonFrank working up diagnostics and Quality "thinking" |
Guidelines for Traders |
Done |
| 3rd week of March |
ClarkswoodSteering Committee |
First visits |
Done |
| 4th week of March |
Travis Perkins |
First visits |
Done |
| 1st week of April |
DLH (1/4) |
First visits |
Done |
| 2nd week of April |
Finnforest (10/4)All companies |
First VisitSecond visits |
DoneLatham's done (with ERM) |
| 3rd week of April |
All companies |
Second visits |
With ERM |
| 18th-21st April |
Easter weekend |
|
|
| 4th week of April |
All Companies |
Second visits |
With ERM |
29/4 2.30 pm, Carlton Club
|
1st CSR Workshop |
Feedback on approach, design, guidelines |
ERM participating |
| May/June |
All 6 |
2nd and 3rd visits |
|
| Early June |
2nd SCM |
|
|
| July-Sept |
No visits |
Write up and reporting |
|
| 14th - 31st July |
FLEGT training |
TTF input in last week |
|
| 9th - 23rd August |
CSR annual holiday! |
|
|
| Sept |
2nd CSR Workshop3rd SCM |
Finalise guidelines |
|
| September 18th |
TTF National Conference |
Feedback to TTF |
Cambridge University college |